2 million euro per year for next 4 years allocated
Marian College
The works to the right bank at Marian College are complete and the path is now open.
Lansdowne Road
The original date for completion of the works on the left bank at Lansdowne Road is 3rd quarter 2012 and it is still expected that works will be completed along that time frame.
Emergency Works
Most of the emergency works will be completed by the end of the third quarter of 2012. However, the reconstruction of the 2metre(6 feet approx) high concrete flood wall from the railway to Beatty’s Avenue is a substantial amount of work, some 250metres in length, and will, most likely, continue until the first quarter of 2013.
The wall on Anglesea Road near the RDS is being monitored and will be repaired if it deteriorates further. Otherwise, it will be repaired as part of major works to take place, probably in 2014.
Some emergency work has already been carried out at the Licensed Vintners’ Association.
River emergency maintenance and reconstruction on the embankment at the LVA on Anglesea Road are also planned.
Phases upstream of tidal section of Dodder
Dublin City Council will complete the draft Part 8 and Environmental Report and these will be submitted to the City Planning Department for comments.
Dublin Flooding Initiative
The Dublin City Council Report is at draft Final Stage, and when completed will be presented to a subsequent Strategic Policy Committee meeting.
Financial Expenditure
The Office of Public Works has projected financial expenditure of between €1M and €2M for each of the next four years.